Montrose Boulevard Improvements Project

About the Project

The Montrose Boulevard Improvements Project was designed to address drainage issues while improving mobility, safety, and overall beauty within the beloved Montrose community. Drainage improvements for outdated stormwater infrastructure within the boulevard are long overdue, and the Montrose TIRZ is focusing on Segment 1 (W. Clay Street to Allen Parkway) of the project at this time. Importantly, no planning or design activities have begun related to Segment 2 (US-59 to W. Clay Street) of the project.

Project Map

Segment 1 of the Montrose Boulevard Improvements Project will:

  • Improve drainage, with large underground storm boxes
  • Improve roadway mobility and safety for all users
  • Promote a pedestrian-friendly environment
  • Reconstruct pavement, driveways, medians, and sidewalks
  • Replace aging utilities
  • Provide greater accessibility to businesses along the boulevard
  • Improve intersection safety and upgrade traffic signals
  • Replace streetlights to meet requirements
  • Protect healthy, well-positioned mature trees
  • Plant new trees
  • Provide a shared-use path on the east side from W. Clay Street to Allen Parkway, connecting pedestrians, bicyclists, and those with disabilities to trails along Buffalo Bayou
  • Provide first- and last-mile bike connections supporting the local and regional “All Ages and Abilities” bike network

It’s About…

Drainage:
Montrose Boulevard serves as the drainage spine for the Montrose area. Through this project, we are working to address drainage issues in problem areas in the vicinity of the project and enhance our long-term capabilities.

Mobility:
We are creating accessibility and comfort for all users by connecting with the east-west biking and walking routes as well as access to Buffalo Bayou Park. We also provide greater accessibility to merchants and restaurants along the Boulevard.

Safety:
As part of the plans, we are creating a buffer with six-foot planting zones behind the curb where we place trees. Additionally, visibility for both pedestrians and vehicles will be enhanced.

Beauty:
We are creating both a healthy tree canopy as well as opportunities for public art. Developing a beautiful natural and created environment has always been important in our Montrose Boulevard redevelopment.

The Montrose TIRZ completed a drainage study in 2019 that highlighted areas of flooding. The project will improve the drainage system by replacing the existing 48-inch and 54-inch pipes with 10-foot by 10-foot boxes. These drainage improvements are designed to accommodate a two-year rainfall event, or five inches in 24 hours, to help mitigate flash flooding in the area and provide five acre-feet of detention.

10-foot by 10-foot boxes

The project follows all the City of Houston’s design requirements related to drainage, reconstruction of the roadway, upgrade of all the utilities below the roadway, adding the larger safety zone, and providing accessible routes for all while keeping the image of the Boulevard in our goals.

The primary safety facets include the shared-use path and larger sidewalks along with a significant increase in the safety zone between the street and the sidewalk where we will add 137 trees.

W Dallas to Allen Pkwy Typical Section
W Clay to W Dallas Typical Section

Project Status

The Montrose TIRZ has submitted final design plans for Segment 1 (W. Clay Street to Allen Parkway) of the Montrose Boulevard Improvements Project. Approval of final design plans for Segment 1 are currently pending review by the City of Houston.

An anticipated construction timeline for Segment 1 of the project will be determined following review and subsequent approval of the final design plans by the City of Houston. The anticipated cost for Segment 1 is $14.7 million, including the bridge over Allen Parkway to Buffalo Bayou Park.

Project Background & Community Engagement

The process to develop the Montrose Boulevard Improvements Project began with a drainage study in 2019 to determine how to improve flooding and drainage within Montrose. Increasing drainage capacity from the existing 48-inch and 54-inch circular pipes to a 10-foot by 10-foot box culvert was the key driver in prioritizing the project, as it can significantly reduce flash flooding during rain events.

Next, a livable centers study was conducted to determine community priorities for infrastructure in the area. This study revealed that the Montrose community desired an improved pedestrian realm to make it easier and safer to walk and bike in Montrose, that prioritized street trees and shade cover, and preserved legacy oaks, particularly along the southern end of the corridor.

Next, the design process began and an initial plan was presented to the public in December 2022. Since then, the Montrose TIRZ has held four public meetings for Segment 1 of the project, solicited community input, and responded to hundreds of questions and concerns from the community.

The Montrose TIRZ has carefully considered and incorporated several improvements to the project design as a result. The feedback received to date has addressed several topics of concern, including pedestrian safety, tree preservation / maintaining a shaded pedestrian realm, and bicycle facilities. As a result, the Montrose TIRZ has incorporated the following elements into the project design while striving to achieve a balanced design approach:

  • A 10-foot-wide shared use path
  • Improved pedestrian safety for signalized and closed median intersections
  • Opportunities to incorporate public art
  • Preservation of many healthy trees and additional tree plantings along the project corridor